HYDROSTADIUM provides comprehensive services to extend the service life and improve the performance of existing hydroelectric power plants. We combine technical diagnostics, equipment modernisation and operational monitoring to optimise the production and safety of the facilities.
Access the details of a project by selecting a point on the map.
Storm Alex severely affected the Alpes-Maritimes on 1 October 2020. The damage assessment was very serious: 13,000 people affected, 18 dead or missing Destroyed roads, flood protection...
Repair of 2 sections of the gallery, each 35 lm long, to ensure the gallery’s watertightness and mechanical continuity. Main technical features Gallery lined over 30 cm with...
Project management for the complete renovation of the Chavaroche scheme (7.8 MW) and the construction of a small hydropower plant for turbining the reserved flow (90 kW). Main...
Project management for the complete rehabilitation of the Notre-Dame de Briançon development (3.4 MW), including detailed design studies for the penstock. Main technical features Ø...
Repair of the headrace tunnel of the Breil development. Main technical features Pressurized tunnel, 2,974 ml long, with an internal diameter of 2.8 m; surge shaft with an internal...
The bypass river enables fish passage around the Petit and Grand Rochepinard weirs on the Cher, while also providing facilities for recreational and sports whitewater activities. It is located on...
The Nottingham whitewater course is more than thirty years old. The English Canoeing Federation wished to optimise this course through a better distribution of gradients and the installation of...
At the request of the Ivrea canoe club, HYDROSTADIUM carried out an assessment in early 2007. The club wished to modify the end section of the whitewater course to make it more attractive and...